CWA has acquired the right-of-way (ROW) for the entire project – pump station, pipeline, canal, and canal maintenance facility. Portions of the ROW are heavily wooded/vegetated and CWA desires to have these areas cleared to facilitate the completion of the designs and allow access during the bidding phases. Total clearing areas are approximately 300 acres.

 

CWA prepared a design/bid package which specified the requirements for this ROW clearing. The design was completed in April 2016 with bidding from April to May 2016. The contractor mobilized in June 2016 and will be completed by September 2016.

 

ROWClearingSchedule